Wivenhoe overhaul finishes early and under budget

06-Jul-2018 2:29 PM

The $11.8 million major overhaul of Unit 2 at CS Energy’s Wivenhoe Power Station has finished ahead of schedule and under budget.

Originally scheduled for 92 days from 3 April – 3 July, the unit was returned to service and available for commercial use on 26 June.
 
More than 54,300 hours were worked on the overhaul by CS Energy employees and contractors MHPS, Cleanaway, McElligotts, and In Place Machining.
 
The overhaul had a peak workforce of 120 people on site, which comprises the power station’s permanent workforce of 11 and more than 100 contractors.
 
The overhaul included statutory maintenance, sandblasting and repairs to the pump suction conduit and turbine spiral casing.
 
A further $3.08 million was allocated for the refurbishment of the guard gate at Wivenhoe’s upper reservoir Splityard Creek Dam.
 
Wivenhoe has two generating units with a combined capacity of 570-megawatts and is the only pumped storage hydroelectric plant in Queensland.
 
The peaking power station performs a valuable role providing fast response power during high electricity demand periods.
 
ENDS
 
Visuals available:
 
A print quality photo of McElligotts painting the Unit 2 internals during the overhaul can be downloaded at: https://www.dropbox.com/s/oawl1ph2sqduvx6/McElligotts%20workers%20painting%20the%20internals%20of%20Wivenhoe%20Power%20Station%20during%20the%20overhaul.png?dl=0
 
A 50 second video compilation of the Wivenhoe Power Station overhaul is available in various file sizes and formats at: https://www.dropbox.com/sh/ua969h8x943wrgr/AAAhc3crhLT2dWhXBxQqwDGma?dl=0
 
Media enquiries
CS Energy Media Line 07 3854 7399
 
About CS Energy

CS Energy is a Queensland energy company that has more than 400 employees, operates three power stations and has a trading portfolio of 4,035 megawatts.

CS Energy operates the 1,510 megawatt Callide Power Station near Biloela in Central Queensland, the 750 megawatt coal-fired Kogan Creek Power Station, near Chinchilla in South West Queensland and the 500 megawatt pumped storage hydroelectric Wivenhoe Power Station, near Esk in South East Queensland. CS Energy’s coal resources include the Kogan Creek Mine.

The company is also party to the Interconnection and Power Pooling Agreement that entitles the company to trade the output of the Gladstone Power Station in excess of the requirements of the Boyne Aluminium Smelter.

CS Energy Chief Executive Officer Martin Moore is on the Board of the Australian Energy Council, which represents major electricity and gas businesses operating in competitive wholesale and retail energy markets.

Topic: General News

Media contact

About us